A 50MWh Junext industrial & commercial energy storage system was installed at a large manufacturing park in Guangdong, focusing on peak shaving and valley filling and renewable energy integration. The system seamlessly connects with the park’s existing solar panels and power grid, complying with ISO and CE safety standards.
The professional team completed on-site installation and commissioning in 25 days. Thanks to the modular design, the installation minimized production disruption. Post-commissioning, the park reduced peak-time electricity costs by 32%, achieved 96% energy utilization efficiency, and secured reliable backup power during grid outages, demonstrating the value of industrial energy storage solutions.